From classrooms to courtrooms, the battle of Dr Ciza ThomasISL 2026/27: Chennaiyin FC snap winless run with 2-0 win over Mumbai CityManipur capital railway connectivity moves closer to reality as CRS begins safety inspectionWoman, lover arrested for killing mother-in-law in Bihar’s PurneaKarnataka: Embarrassment for Cong govt as ASHA workers continue protest despite CM's assurancesMP CM congratulates Indian women on historic Asian Champions Trophy triumphIWL 2026/27: Late double strike powers Gokulam Kerala FC to 3-1 victory over Kickstart FC8 cases registered in Rs 8.68 crore GST fraud in MP's Jabalpur, probe onShiv Sena (UBT) issues three-line whip ahead of LS session over delimitationGujarat CM inaugurates Rs 7.5-crore Meher Samaj Bhavan in Porbandar

Advertisement

Manipur capital railway connectivity moves closer to reality as CRS begins safety inspection

Safety inspection of the new Khongsang-Awangkhul section brings Imphal a step closer to direct rail link

Follow The Hawk on Google News+ Follow
Manipur capital railway connectivity moves closer to reality as CRS begins safety inspection

Advertisement

Guwahati: The vision of connecting Manipur's capital Imphal to the national railway network has moved a step closer to reality with the commencement of a two-day statutory safety inspection by the Commissioner of Railway Safety (CRS) of the newly constructed 8.93-km railway track, officials said on Saturday.

The Northeast Frontier Railway (NFR) Chief Public Relations Officer (CPRO) Kapinjal Kishore Sharma said that the NFR's Commissioner of Railway Safety (CRS) Brijesh Kumar Mishra commenced a two-day statutory safety inspection of the newly constructed 8.93 km Khongsang-Awangkhul broadgauge section in Manipur earlier in the day.

Advertisement

The section falls under the Lumding Division of the NFR and forms part of the 111-km Jiribam (adjoining Assam)--Imphal New Broad-Gauge Line Project.

Also readGujarat CM inaugurates Rs 7.5-crore Meher Samaj Bhavan in Porbandar

The inspection will assess the section's readiness prior opening for passenger and freight traffic.

Sponsored

On the first day, the CRS inspected the stretch from Khongsang railway station to tunnel number-24 by special train.

The inspection covered the newly laid track and associated railway infrastructure along this part of the alignment, completing the first leg of the two-day programme, CPRO Sharma said.

Also readSettle in Rewa and have as many children as you want: BJP MP

On Sunday, the CRS will resume the inspection from tunnel number-24 and cover the remaining stretch up to Awangkhul railway station.

A speed trial run will also follow on the newly laid track and an instrumented observation car will record the riding behaviour of the train during the trial run as part of the safety assessment.

The 110.625-km Jiribam-Imphal project is being developed in phases to connect Manipur's capital to the national railway network.

Advertisement

The first two phases brought the line from Jiribam up to Khongsang, and the opening of the section now under inspection, subject to statutory authorisation, will extend it further to Awangkhul.

The route traverses hilly terrain and includes 11 stations, 54 tunnels spanning a combined 66.47 km, 15 major bridges and 116 minor bridges.

Among its major structures is bridge number-164 at Noney, which has a 141 metre high pier.

The NFR CPRO said that subject to CRS authorization at Awangkhul, the seventh station of Jiribam-Imphal New Line, will be the next to open to rail traffic.

Its opening will extend the operational railway line beyond Khongsang, bringing Manipur's capital a step closer to direct rail connectivity.

A senior official of the Northeast Frontier Railway (NFR) said that the railway line connecting Imphal to Jiribam town, bordering southern Assam's Cachar district, is a critical 111-km infrastructure project worth around Rs 22,000 crore, which is expected to be fully operational by June 2029.

Get The Hawk first on Google

Add The Hawk as a preferred source and Google shows you more of our stories in Top Stories. Follow us on Google News too.

Share this story

Advertisement

Rail connectivity to Tripura, Mizoram, Manipur disrupted after goods train wagon derailment in AssamRead next →Rail connectivity to Tripura, Mizoram, Manipur disrupted after goods train wagon derailment in AssamAssam · 28 Nov 2026, 09:28 PM IST